12
Mar
Transaction
1. Customer’s deposit payment slip.
Production
1. Product nozzle completed.
2. Product control cabinet completed.
3. Product nameplate completed.
4. Product is finished.
Transportion
1. Fog cannon packaged and sent to Singapore.
read more
30
Sep
1.17th August.2020-UK-Fog Cannon+Fogging Machine-Received customer’s back receipt.
2.Next we will update the production
3.14th September.2020-Products have been tested before leaving the factory, and have been packaged and shipped.
Transation-Second Order
Country:The United Kingdom
Customer Number:101078414839
Product Name: 30m Fog Cannon+10kw generator set
1.24th June 2021, We received the second order from the customer.
Production
2.10th July 2021
The cannon body and base of the fog cannon have been made, and the fan... read more
06
Mar
Transaction
1. Customer’s deposit payment bill before production.
Production
1. Testing unit operation.
Production
2. Ready to ship.
Production
3. In shipping warehouse.
read more
09
Jun
Transaction
Country:Vietnam
Product:centrifugal fan and impeller
1. Customer’s payment bill before production.
Production
1. Customer’s drawing before production.
2. Have started cutting raw material. Automatic NC cutting.
3. The fan base has been welded by technicians with many years of... read more
03
Aug
Transaction
Country:Thailand
Product:centrifugal fan
1.Customer is payment bill before production.
Production
1. The cutting of the fan has been completed.
2. The molding of the fan has been completed.
3. The external procurement of the fan motor has been... read more
29
Apr
1.24th Apr.2020-Canada-Electrostatic Sprayer-Receive the customer’s bank receipt.
2.Next, we will update the production of the product.
read more
12
Jul
Transaction
Country:Afghanistan
Product:Air-cooled chiller
1. T/T 30% to be paid as deposit.
read more
14
Apr
2019-04-14:Cargo is ready and waiting for painting. Waiting for the balance payment.
read more
09
Apr
Transaction
Country: Hongkong, China
Product Name: Dust collector-MF9015
1.Customer’s payment bill before production.
Production
1.The performance test of the dust collector is completed.
read more
20
Nov
Transaction
Customer’s payment bill before production.
2. Customer’s payment bill after production.
Production
1. Provide customers with drawings and produce according to the drawings.
2.The Centrifugal fan are in production.
3.The Centrifugal fan are assembled by our workers.
4.Centrifugal fan pictures to... read more