Order Tracking No.:SCY20211029-Guatemala-Fan Blower for Biomass Steam Boiler

1.Customer’s 100% payment bill before production, full trust.

1. Have been finished cutting raw material.

2. The two blowers have been finished shot blasting, the housing has completed the welding process.

3. Two blowers have all been painted in gray as customers requirement.

4. Professional Testing in the laboratory before delivery.

5. The goods have been sent to port and ready to ship. Waiting for the vessel.