1.21th May.2020-Peru-Mist Cannon-Receive the customer’s bank receipt.
2.The product has finished production.
3.03th Jun.2020-BILL OF LADING
1.21th May.2020-Peru-Mist Cannon-Receive the customer’s bank receipt.
2.The product has finished production.
3.03th Jun.2020-BILL OF LADING
Transaction 1. My deposit receipt from the client. Production 1. Dec.13:Compressor test images. 2. Dec.14:The crew is preparing for testing. 3. Dec.21:Compressor packaging in progress. read more
Transaction Country:United Arab Emirates (UAE) Product:Centrifugal Blower 1.50% Deposit payments in advance from customer. Production 1. The casing, impeller, and bracket parts have been finished lofting,marking-off and cutting. 2. The impeller and casing of the centrifugal fan have been assembled and... read more
Transaction Country:Philippines Product:Centrifugal Blower 1. 50% Deposit payments in advance from customer. 2. To match the on-site piping and save time and labor costs for installation, the customer has placed an additional order for fan accessories. The final payment for the fans and... read more
1.13th May.2020-South Africa-Fogging Machine-Receive the customer’s bank receipt. 2.14th May.2020-Production completed. 3.26th May.2020-Ship by sea. read more
Country: Peru Product name: Impeller 2.The impeller has been produced and tested for dynamic balance, and it was sent out via FedEx last Saturday 3.The goods have been sent to Peru and are undergoing customs clearance. The customer will receive the goods within 3 days read more
Country:Indonesia Product: Centrifugal fan Heat exchanger Filter bag Filter bag cage Rotary valve Pulse valve Pulse valve controller 1.17th Dec.2020 Received customer’s bank slip 2.Production progress update:Centrifugal fan 3.Production progress update:Heat exchanger 4.Production progress update:Filter bag cage 5.Production progress update:Filter bag 6.Production progress update:Rotary valve 7.Production progress update:Pulse valve 8.Production progress update:Pulse valve controller 9.2019-04-14: Cargo is ready and waiting for... read more
Transaction 1. 30% Deposit payments in advance from the customer. Production 1. The fan casing has been completely welded. 2. The fan casing has been completely welded. read more
Transaction Country Name: Egypt Product Name: Centrifugal Blower 1.100% Deposit payments in advance from the customer. read more
Transaction Country:Guatemala Product:Fan Blower for Biomass Steam Boiler 1.Customer’s 100% payment bill before production, full trust. Production 1. Have been finished cutting raw material. 2. The two blowers have been finished shot blasting, the housing has completed the welding process. 3. Two... read more